Anti-data-center protests spread across 49 U.S. states, blocking about $68 billion in projects in Q2
As of the end of September, 843 anti-data-center protest groups had emerged across 49 U.S. states, with about 700,000 participants, up from just 24 states, 188 organizations, and 250,000 people in May. About three-quarters of the 146 canceled or delayed projects tracked by S&P Global Ratings involved local opposition; Data Center Watch counted at least 45 projects blocked or delayed in the second quarter of 2026, involving about $68 billion in value. Pennsylvania signed an executive order on August 18 requiring data centers to meet stricter environmental, transparency, and community engagement standards and to bear the cost of new energy infrastructure; Goldman Sachs estimates that North American AI computing power rental prices will rise 12%-18% year on year in 2026.
Why read this
AI score 76
The article uses protest scale, the value of blocked projects, and electricity price data to show how data center siting disputes are driving up AI infrastructure costs.
Topics
Body · AI translation
[[**Anti-data-center protests in 49 U.S. states have threatened hundred-billion-dollar projects; the core issue is that residents bear the costs of electricity, water, land, and housing prices while lacking decision-making power and a share of the benefits. AI infrastructure costs, site selection, and computing power rents will be affected over the long term.**
**Key Points**
**1. Anti-data-center protests have spread across the United States and are directly blocking projects**
As of the end of September, 843 groups and about 700,000 people in 49 states had participated; in May, it was only 24 states, 188 organizations, and 250,000 people. Of the 146 canceled or delayed projects tracked by S&P, about three-quarters involve local opposition.
**2. The core contradiction is that residents bear the resource costs but lack benefits and decision-making power**
A 200MW data center consumes as much electricity annually as 400,000 people; by 2028, cooling water use will reach 68 billion gallons, and about two-thirds of new projects are located in water-scarce areas; housing prices within 3 kilometers fell by an average of 11.7% from 2024 to 2025. Although Loudoun County contributes $1.2 billion in tax revenue, accounting for 39% of the budget, the benefits are concentrated in the construction period, and confidentiality agreements also weaken the right to know.
**3. Tightening policies and rising residents' bargaining power are pushing up AI infrastructure and computing power costs**
On August 18, Pennsylvania required data centers to meet environmental, transparency, and community participation standards and to bear the cost of new energy infrastructure. In Q2 2026, at least 45 projects were blocked or delayed, worth about $68 billion; Goldman Sachs predicts that North American AI computing power rental prices will rise 12%-18% year on year. 2026-11-03 19:42 Protests erupted in 49 U.S. states Gelun Quick Read
Any technology, no matter how it is packaged or hyped, must ultimately serve people. If it deviates from this premise or even hinders people, its value will inevitably be greatly diminished.
According to tracking data from Data Center Watch: as of the end of September, 843 highly organized anti-data-center protest groups had emerged in 49 U.S. states, and about 700,000 people had participated in rallies, marches, and petition protests.
In May, the figures were still 24 states, 188 organizations, and 250,000 people.
Moreover, as the midterm elections approach, related incidents have become more frequent, and the current figures must have swelled to an exaggerated level.
ACLED counted before the midterm elections that demonstrations against data centers in the United States this year had reached as many as 330.
S&P Global Ratings data on October 23: of the 146 canceled or delayed data center projects tracked, about three-quarters involve local opposition.
Ballotpedia's latest statistics on November 2: on November 3, there were 41 related proposals in 10 states, of which 28 were intended to restrict development and 13 to promote development.
In urban planning, there is a term called NIMBY, Not In My Backyard.
But now, out of resistance to data centers, this term has escalated to NOTE, Not Over There, Either (building over there is also not okay; nowhere is okay).
Because ordinary people's vital interests are threatened.
First, the oft-repeated electricity issue.
A standard AI training data center with 200MW installed capacity, calculated at the industry average load rate of 86%, consumes as much as 1,500GWh of electricity annually.
That is equivalent to the annual electricity consumption of 400,000 people.
The International Energy Agency estimates that from 2026 to 2030, U.S. electricity consumption will increase by more than 420 billion kWh in total, with about half of the increase coming from data centers.
Data released by the U.S. Energy Information Administration on October 23 show that the average residential electricity price in August reached 18.16 cents per kWh, up 3.4% year on year.
It is expected that the average residential electricity price will reach 18.7 cents in 2027, a cumulative increase of about 13.3% compared with 2024.
This aspect is well known, so I will not elaborate further.
In short, tech companies want to change the world, but why should ordinary people pay for it?
But the cost is that freshwater consumption is very exaggerated.
Lawrence Berkeley Lab estimates that by 2028, direct cooling water use by U.S. data centers will reach 68 billion gallons, equivalent to the annual water use of 2 million people.
Overall it is not much, but it must be viewed by region.
According to Bloomberg data: since 2022, about two-thirds of newly built or under-construction data centers in the United States are located in areas with severe water stress.
For example, Oracle's planned Project Jupiter has a planned investment scale of $165 billion, is expected to create more than 7,000 jobs, and bring $4.7 billion in tax revenue in the future.
For local areas, this is undoubtedly a very tempting investment.
The problem is that the project site, New Mexico, is severely short of water.
Although Oracle has promised to invest $50 million in local water and sewage treatment systems and plans to use agricultural water-saving technology to help farmers save 21 million gallons of water each year.
But in August this year, the New Mexico Supreme Court, at the request of environmental groups, still temporarily blocked the project from drawing water through new wells.
This is where the contradiction lies.
Tech companies believe that the water shortage problem can be solved through technological optimization, infrastructure, and procurement agreements.
In plain terms, if data centers can make money, are they afraid they cannot buy water?
But for local residents, they are unwilling to use existing resources in exchange for future benefits.
Second, land.
For example, in Virginia, a 189-acre plot of land originally approved for 516 homes was sold to Amazon for about $700 million for a planned data center campus.
From the local government's perspective, this choice is very reasonable.
Residential development requires schools, roads, public transit, fire services, and long-term public service investment, whereas data centers have high equipment and real estate value and can generate considerable local tax revenue.
But this clearly infringes on the interests of ordinary people.
When localities attract industry, what they want is tax revenue and jobs.
But a data center costing tens of billions of dollars is full of highly automated robots. Aside from electricians, the long-term operations and maintenance positions actually needed may number fewer than 100.
Residents not only gain no benefits, but also have to pay for the noise and air pollution brought by the server rooms.
According to statistics from the U.S. real estate platform Zillow, homes within 3 kilometers of server rooms depreciated by an average of 11.7% from 2024 to 2025, land liquidity deteriorated significantly, and residents' core assets shrank substantially.
So here is the problem.
The areas most severely affected by noise, electricity costs, and water shortages (such as the Midwest, Texas, Missouri, and Oklahoma) are precisely Trump's core MAGA agricultural and blue-collar base.
Since they can neither offend the base nor abandon the computing power arms race, what should be done?
02
All of the above ultimately boils down to one sentence: the distribution of benefits and decision-making power are unequal.
The economic value of data centers has already been verified.
Loudoun County, Virginia, is one of the most successful cases in the United States.
According to public data, as of March 2026, the area had about 233 data center buildings completed or at various stages of construction, creating more than 17,000 jobs in total.
In fiscal year 2026, data centers contributed $1.2 billion in real and personal property tax revenue, accounting for about 39% of the county budget.
In fiscal year 2027, this is expected to rise to $1.3 billion, reaching 40%.
This revenue has helped Loudoun County continue to lower local tax rates and fund schools, public services, and infrastructure.
But that does not mean they are willing to accept it.
First, the economic benefits created by a project and the costs borne by residents often occur at different times.
Land development for data centers has a strong long-term lock-in effect. Once a company builds large numbers of specialized server rooms, substations, and supporting pipelines, adjusting land use in the future will require very high conversion costs.
This means a single land-use change may determine the direction of local development for decades to come.
During construction, there will indeed be a large number of engineering jobs, equipment orders, and tax revenue.
But after construction is completed, long-term operational positions will decrease significantly, while land occupation and infrastructure demand will continue to exist.
Although the current benefits are attractive, not everyone is willing to overdraft the next few decades.
More importantly, ordinary people's right to know has been violated.
A study published in August by the Federation of American Scientists (FAS) revealed transparency problems in data center development agreements.
The study pointed out that negotiations for some projects are constrained by confidentiality agreements, making it difficult for residents to understand the specific contents of tax breaks, compensation arrangements, and long-term obligations.
By the time specific construction plans enter public view, land acquisition, infrastructure arrangements, and tax agreements have already been advanced for a considerable period.
As a result, the only choice residents have is to oppose the project itself.
Therefore, to fundamentally solve the problem, ordinary people must be allowed to participate in project decision-making and benefit distribution.
Some U.S. state governments have already begun adjusting policies.
On August 18, Pennsylvania signed an executive order requiring data center developers to meet stricter environmental, transparency, and community participation standards and obtain local approval.
The new rules exclude data centers from fast-track permitting, prohibit relevant government departments from signing confidentiality agreements with developers, and require companies to bear the cost of new energy infrastructure.
At the same time, developers must submit more detailed information on water use, energy consumption, and environmental impact, and community benefit commitments must also be legally binding.
In short, it places residents' right to participate, environmental responsibility, and the conditions for using public resources at the core of investment approval.
And this policy change will also alter the negotiating relationship between tech companies and local communities.
In the past, developers often gained a strong bargaining advantage by virtue of investment scale, job opportunities, and tax commitments.
Now, residents are gaining greater negotiating power by organizing protests, pushing for referendums, demanding information disclosure, and filing lawsuits.
This change has already had a substantial impact.
According to Data Center Watch statistics, in the second quarter of 2026, at least 45 data center projects in the United States were blocked or delayed due to local opposition, involving projects worth about $68 billion.
In the first quarter, even more projects were blocked or delayed, reaching 75, involving about $130 billion.
For society as a whole, this change is benign.
The current situation is that more and more developers have money and blueprints, but simply cannot obtain permits.
Goldman Sachs estimates that in 2026, North American AI computing power leasing prices will rise 12%-18% year on year.
Computing power demand is urgent. How exactly should this end?
03
No matter how rich or profitable tech companies are, before moving toward AGI, they must first compromise with public opinion.
Some investors who feel it is none of their business may think that the people participating in protests are completely hindering technological progress.
No matter how you look at it, this idea is wrong.
What American residents are opposing now is fundamentally not data centers, but infringement on their own interests and rights.
They want to know whether, after a company acquires land, it will affect local housing prices; how agricultural and residential water supply will be guaranteed after industrial water use increases; how much revenue schools and public facilities will receive after tax incentives are granted; and who will bear responsibility for the impact of long-term project operations.
What is wrong with defending one's own interests?
Even at the technical level, slowing down may not necessarily be a bad thing. (End of full text) AI Industry Signal Channel: Frontier Technology This content comes from the internet and the original link. The views only represent the author and do not represent Huxiu's position. If there is any copyright issue, please contact hezuo@huxiu.com, and we will verify and handle it promptly. Everyone who is changing and wants to change the world is on the Huxiu APP [ ]