Anthropic spends $3.4 billion to lock in 1.7GW of gas-fired power generation equipment
Anthropic has spent about $3.4 billion to obtain an order for 1.7GW of gas-fired power generation equipment from U.S. power equipment supplier OnePWR Solutions to guarantee power supply for data centers, and the report says this is the largest single power generation equipment purchase by an AI lab in publicly available information to date. The deal was reached in late September this year and involves heavy-duty gas-fired generator sets produced by Caterpillar, and includes the engineering design and construction capabilities needed for installation; because OnePWR had already reserved equipment from Caterpillar about two years ago, Anthropic can receive the equipment successively from the near term to the next two years. Documents Anthropic filed with the U.S. Securities and Exchange Commission show that as of September 30 this year and thereafter, the company has signed committed expenditures of about $895.4 billion for procurement, leasing and other items, most of which is related to computing capacity and infrastructure, and the related spending will continue through 2045.
Why read this
AI score 70
The deal shows that AI companies are shifting from relying on the power grid to directly securing power generation equipment, which helps readers understand the power constraints behind the expansion of computing capacity.
Topics
Body · AI translation
How severe is the AI power shortage? Anthropic spends $3.4 billion to lock in 1.7GW of power generation equipment. Phoenix Tech Download the app for exclusive early access. November 9, 2026, 15:29:42 From Beijing
Phoenix Tech News, November 9 — According to a report by the UK's Financial Times, AI company Anthropic has spent about $3.4 billion to obtain an order for 1.7GW of gas-fired power generation equipment from US power equipment supplier OnePWR Solutions, in order to secure electricity supply for its data centers. This is considered the largest single power generation equipment purchase by an AI lab in publicly available information to date.
The deal was reached in late September this year and involves heavy-duty gas generator sets manufactured by Caterpillar, and includes the engineering design and construction capabilities required for equipment installation. Anthropic did not acquire OnePWR, and the latter's employees did not transfer to Anthropic.
According to the report, OnePWR had already placed an order for the relevant equipment with Caterpillar about two years ago. Anthropic initially planned to buy electricity from it, and then decided to take over this batch of generator set orders. Because the order was formed relatively early, Anthropic can receive the equipment successively from recently to within the next two years, avoiding the problem of continuously lengthening delivery cycles for gas-fired power generation equipment at present.
As the construction of AI data centers accelerates, in addition to chips, power supply and power generation equipment are becoming new resources contested by technology companies. In the past, AI companies mainly relied on utility companies or energy developers for power supply; now some companies have begun to directly lock in power generation equipment to reduce the impact of grid connection and equipment delays.
A recent filing by Anthropic with the US Securities and Exchange Commission shows that as of September 30 this year and thereafter, the company has signed committed expenditures of about $895.4 billion for procurement, leasing, and other items, most of which is related to computing power and infrastructure, and the related expenditures will continue through 2045. (Author/Song Shumei)