Google cleared 250,000 trees for a data center in Finland; regulator ordered work to stop
English text is being prepared.
Google cleared about 330 hectares of forest, estimated at about 250,000 trees felled, to build a data center in Muhos in northern Finland, and carried out large-scale land clearing before completing the legally required environmental impact assessment. The Finnish Permitting and Supervision Agency (LVV) earlier this month ordered Google to suspend construction at two sites, Muhos and Otanmäki about 100 kilometers away, and to stop activities that would significantly alter the environment by October 23. Environmentalists estimate that another approximately 150,000 trees were felled in Otanmäki, and Google's Finland country head has apologized for the forest clearing.
Why read this
AI score 59
The report presents the specific conflict between data center siting and local environmental regulation, as well as the timeline of the regulator's order to stop work.
Topics
Body
芬兰森林惨遭“剃光头”:谷歌为建AI数据中心非法清场25万棵树IT之家下载客户端 独家抢先看2026年10月23日 14:58:35 来自山东Updated 2026年10月23日 15:46:57
IT之家 10 月 23 日消息,英国《卫报》昨日(10 月 22 日)报道,谷歌为了在芬兰北部穆霍斯(Muhos)建设数据中心,清除了约 330 公顷(330 万平方米)森林,估计砍伐约 25 万棵树,且在未完成法定环境影响评估前进行大规模土地清理,甚至移除了表土。
IT之家援引博文介绍,当地居民与环保组织批评称,工地如今只剩泥泞空地、机械辙痕和堆积的树根;泥水还可能流入最终汇入奥卢约基河的溪流,引发对水质和生态的担忧。
芬兰许可与监督局(LVV)本月早些时候要求谷歌暂停穆霍斯及约 100 公里外奥坦迈基(Otanmäki)两个工地的施工,并须在 10 月 23 日前停止会显著改变环境的活动;若未遵守,监管机构可能启动执法程序并处以罚款。
环保人士估计,除穆霍斯的 25 万棵树外,奥坦迈基另有约 15 万棵树被砍伐,称谷歌在芬兰非法砍伐 40 万棵树。由于属非法砍伐,相关木材也无法出售给木材加工企业。谷歌芬兰区负责人已就清林道歉。