TechCrunch AI更新于 10月13日 13:26

Crusoe 放弃 12.5 亿美元采购 Boom 涡轮机用于 AI 数据中心的计划

Crusoe abandons $1.25B plan to use Boom turbines at AI data centers

AI 导读

Crusoe 已终止与 Boom Supersonic 的涡轮机合作,原计划斥资 12.5 亿美元采购 29 台 42 兆瓦 Superpower 涡轮机,首批交付原定 2027 年开始。Boom CEO Blake Scholl 称 Crusoe 近期主要电力结构不再包含涡轮机,Crusoe 回应称能源计划未变,仍会用涡轮机,只是不用 Boom 的。Boom 表示明年将向其他站点交付约 250MW Superpower,目标 2028 年达到 1GW。

正文

当前显示原文,中文全文译文尚未就绪。

Crusoe, a Denver-based AI data center startup that recently raised $3.9 billion , has ended plans to use a new line of stationary power plants developed by fellow Denver company Boom Supersonic.

Founded in 2018 as a bitcoin miner that ran on excess natural gas from oil fields, Crusoe has since become one of the biggest builders of AI data centers , including a massive campus in Abilene, Texas, that supplies computing power to OpenAI.

Boom Supersonic, which is developing a supersonic passenger jet called Overture, launched a new business last year to sell a version of the engine it’s developing for that jet as natural gas-fired stationary power plants. Its Superpower turbine shares about 80% of the same parts with that airborne engine, called Symphony.

Crusoe had signed on to be the first customer for this business, agreeing to spend $1.25 billion on 29 of Boom’s 42-megawatt Superpower turbines. The first deliveries were supposed to begin in 2027. But that deal has since fallen apart, according to Boom Supersonic CEO Blake Scholl.

On Friday, in a post on X , after congratulating Crusoe founders Cully Cavness and Chase Lochmiller on the company’s recent raise, Scholl said the companies are no longer moving forward with the turbine launch partnership. Although he did note that other customers were in its pipeline.

“Boom will be delivering about 250MW of Superpowers next year to other sites, and we’re targeting 1GW in 2028,” Schooll wrote. “We’re grateful for the help Crusoe gave us in shaping Superpower and continue cheering for their successes. The future is long, and we look forward to potentially teaming up if/when turbines become part of their primary power mix.”

Scholl’s initial post include a line which he later removed: “The TL/DR is that turbines are no longer part of Crusoe’s near term primary power mix at Abilene/etc., so a launch partnership just didn’t make sense.” Crusoe spokesperson Andrew Schmitt subsequently told us that the company’s energy plans “haven’t changed” and that it still plans to use turbines, “just not Boom’s.”

“We build AI factories from the power up, and we’re bringing new campuses online across the country, powered by innovative energy sources,” Andrew Schmitt said in an email. “As our portfolio grows, we stay flexible, choosing the energy solutions that are right for each site as its needs evolve — including turbines, along with wind, solar, batteries and the grid. While Boom has been a great partner, the partnership isn’t the right fit today. We wish them well.”

Crusoe’s initial 1.2 gigawatt data center in Abilene that was built for Oracle and OpenAI is powered by the grid, according to the company. There is also a gas-turbine power plant that is used for backup power only. Crusoe is also building a 900 megawatt data center in Abilene for Microsoft, which will be powered by on-site gas turbines.

Losing its launch customer is seemingly a setback for Boom, which raised $300 million last year, largely to commercialize the new business. The idea, Scholl told TechCrunch at the time, was to use profits from the stationary power plant business to fund the development of Overture.

Scholl could not be reached for comment before publication; TechCrunch will update this article if he responds.

The article was updated to reflect Scholl’s edit to his own post on X.

来源

TechCrunch AI