Firmus 与 PLDT 数据中心 IPO 遇阻,亚太数据中心热潮放缓

Speed Bumps Slow Asia’s Data Center Gold Rush

AI 导读

澳大利亚 Firmus 撤回 AU$7.1 亿(US$4.97 亿)ASX 上市申请,改为寻求最高 $3 亿私募融资;菲律宾 PLDT 将数据中心 REIT(Vitro)上市推迟至 2027 年,理由是市场状况与利率上升。印尼西爪哇叫停 BDX 的 640MW 项目,泰国暂停 166 个数据中心项目,马来西亚能源委员会则警告数据中心令电力需求年增速从 1.5%-2% 升至近 10%。

正文

Firmus and PLDT pulled data center IPOs this week while governments pressed pause on development in the latest hurdles to Asia’s data center boom.

October 9, 2026

Asia-Pacific's hectic data center rollout has hit a series of speed bumps. The most dramatic by far was the collapse Friday of Australian-based Firmus’ planned AU$7.1 billion (US$4.97 billion) IPO, which had been expected to be the biggest ASX debut since Telstra’s 1997 IPO.

Firmus, a neocloud company whose shareholders include Blackstone, Jane Street and Nvidia, withdrew its ASX listing application Friday and said it would seek up to $3 billion through private fund-raising, the Financial Times has reported.

It had struggled to win market support at its target price of around AU$11 ($7.67), but even after it offered to cut the price, investors did not have the appetite.

Trading in Maas Group, one of Firmus' shareholders, was halted Friday after the stock dropped 27% in two days. Maas Group has a 3.2% stake in the company as well as outstanding contracts with Firmus worth AU$727 million ($507 million).

Two days earlier, Firmus had been dumped by CDC Data Centers from their joint AI infrastructure project in Australia after CDC had become troubled by Firmus’ southeast Asian expansion, which had not been a part of the original partnership.

PLDT delays IPO to 2027

Firmus' wasn't the only IPO to go south this week. Philippine telco PLDT put its data center REIT listing on hold until 2027, blaming the decision on higher interest rates. The REIT, Vitro, was expected to generate as much as 24.2 billion Philippine pesos (US$385.1 million) on the Manila bourse.

PLDT said in an exchange filing it had decided to delay the IPO until 2027 due to "current market conditions and rising interest rates." But it said it was committed to the IPO as an important part of its asset monetization and deleveraging plans.

The Philippines' central bank last month hiked interest rates by 25 basis points and is widely expected to announce two more rate rises by the year's end.

Southeast Asian governments have also been forced to press pause on the AI boom. Last week, Indonesia's West Java province halted a 640MW project by Singapore–based BDX, claiming it had not received key approvals, including an environmental assessment.

A month ago, Thailand suspended 166 data center projects – of which 49 were under construction and 117 awaited approval – to allow government committees to write new industry rules that would set standards and maximize the economic benefit to Thailand.

In Malaysia, the center of Asia's data center boom, officials are anxious about soaring the new digital infrastructure's power consumption. Electricity demand growth has gone from 1.5%-2% annually to nearly 10% due to data centers, Siti Safinah Salleh, head of the Malaysian Energy Commission, is reported to have said.

Salleh warned that recovering energy costs from data center operators is difficult because many are on short-term contracts and have refused to make long-term commitments.

This article was originally published on Light Reading.

Contributing Editor, Light Reading

Robert Clark is a Contributing Editor at Light Reading.

Want more Data Center Knowledge stories in your Google search results?

Editor's Choice

Aug 21, 2026

Want more Data Center Knowledge stories in your Google search results?

Join the entire data center ecosystem September 21 – 23, 2026, at the Gaylord Texan Resort & Convention Center in Dallas, TX.

来源

Data Center Knowledge