404 Media 报道后,得州用于数据中心审批的 STEERS 门户被关停
Portal Texas Used to ‘Rubber Stamp’ Data Centers Down After 404 Media Reporting
在 404 Media 报道得州州长 9 月叫停数据中心审批后仍持续发证之后,得州关闭了自动施工许可申报系统 STEERS,并暂停了 17 个数据中心项目的施工许可。TCEQ 表示,暂停门户是为了让工作人员逐项审查申请是否与数据中心相关;被暂停的 17 个许可均涉及雨水施工审批。FracTracker Alliance 研究员 Sam Law 称,这些许可此前被自动“盖章”通过,其中包含本周一、周二获批的 OpenAI 和 Amazon 相关项目。
正文
Go ad free
Commissioners in Texas said they’re making sure ‘all applications are reviewed by agency staff to determine if they are related to data centers.’
Construction equipment sits idle within the construction site of a massive hyperscale data center building that's under construction on a 135 acre parcel of land near the intersection of Loop 1604 and Military Drive West in San Antonio, Texas, USA, on January 26, 2025. (Photo by Carlos Kosienski/Sipa USA)(Sipa via AP Images)
Texas has shut down the web portal for its automated construction permit filing system and suspended construction permits of 17 data center projects. The change came after 404 Media reported that a group of Texans discovered the state had continued to issue construction permits related to data centers despite Governor Greg Abbott calling for a pause in September.
On Monday, the watchdog groups FracTracker Alliance and Public Citizen published reports detailing more than two dozen permits issued to Texas data center projects. On Tuesday, the website for STEERS – an application filing system for construction projects run by the Texas Commission on Environmental Quality (TCEQ) – returned a 404 error.
The TCEQ portal as it appeared on Wednesday afternoon.
By Wednesday, the site had this message on it: “TCEQ’s electronic filing application used for automatic authorizations has been temporarily shut down to ensure all applications are reviewed by agency staff to determine if they are related to data centers.”
View this post on Instagram
Before TCEQ shut the portal down, 404 Media viewed 17 different permits related to data center projects and saw that they’d been moved from “active” to “suspended” in the TCEQ central registry.
“STEERS is a portal that TCEQ uses to rubber stamp construction approvals,” Sam Law, a researcher at FracTracker Alliance told 404 Media. “It seems like they forgot about it and the portal has been quietly issuing approvals since the governor’s order for a pause, including for OpenAI and Amazon this Monday and Tuesday.”
The 17 suspended permits are related to stormwater construction, an approval that allows construction companies to raise and level ground. It’s a key, and sometimes final, part of the approval process for any construction project in Texas.
'It Ain't Right:' Texas Said It Would Halt Data Center Permits. The State is Pushing Ahead Anyway“The Caldwell Technology Park [...] the Stargate facility, and a bunch of other very large hyperscale facilities have gotten regulatory approvals [...] so it's not like a real pause."404 MediaMatthew Gault
“Now they’ve taken the unprecedented step of suspending 17 approvals and taking down the whole site as they switch to a more involved human review process,” Law said. “The irony is not lost on me. When fighting the AI data centers build out, it’s nice to have a clear example of how some work is better left to humans.”
Law said he reached out to TCEQ and didn’t hear anything from them. The commission also didn’t respond to 404 Media’s request for comment. “I am very concerned that since contractors are accustomed to this automated approval process, they might not be aware of the suspension and continuing construction at some of the largest hyperscale facilities in Texas,” Law said.