微软因供电问题退出 Nscale 英国 Essex AI 数据中心项目

Microsoft pulls out of AI datacentre project in Essex over power supply concerns | Datacentres - UK | The Guardian

AI 导读

微软因供电问题退出英国公司 Nscale 在 Essex Loughton 的 AI 数据中心项目,不再作为该项目的锚定租户。该项目曾被英国政府称为本国最大的主权 AI 数据中心,原计划明年开放,但英国电网运营商 UKPN 告知最早要到 2030 年代初中期才能提供足够电力。Nscale 表示仍致力于该项目,正探索现场发电等替代供电方案,并称与微软的长期合作关系不受影响。

推荐理由

AI 评分 60

微软退出后,Nscale 的 Essex 数据中心失去唯一公开客户,其 350 亿美元上市计划面临变数。

主题

标签

正文

An artist’s impression of Nscale’s planned datacentre in Loughton, Essex. Photograph: Nscale

An artist’s impression of Nscale’s planned datacentre in Loughton, Essex. Photograph: NscaleMicrosoft pulls out of AI datacentre project in Essex over power supply concerns

Development by UK firm Nscale heralded by ministers as largest of its kind in country loses anchor tenant

The development of a huge AI datacentre hailed by the UK government has received a fresh setback after Microsoft pulled out of the project over concerns about power supplies.

The development by the British company Nscale, heralded by ministers as the country’s largest AI datacentre when it was announced in 2025, was planned to open at Loughton in Essex next year.

Doubts had already emerged about the scheme after the Guardian revealed in March that the location was still an operational scaffolding yard.

Now there are further concerns after Microsoft, one of its largest planned customers and expected to have been the anchor tenant, informed the company that it was pulling the plug on its agreement.

It comes a month after it emerged that power supply problems meant the project would face a lengthy wait before coming online.

Keir Starmer’s government had highlighted the Loughton project when announcing the UK’s AI strategy in 2025, describing it as the “largest UK sovereign AI datacentre”. Datacentres are the central nervous system of AI technology such as chatbots.

The end of the deal with Microsoft, first reported in the Telegraph, means Nscale has lost its only publicly announced customer for the Essex datacentre. It is understood that Microsoft remains on board for another project the company has in Norway.

Nscale, which is backed by tech companies including Nvidia, has positioned itself as Britain’s “sovereign” datacentre provider but the loss of an anchor tenant for its Loughton project could undermine its ambition to float on Wall Street this year with a potential valuation of $35bn (£26bn).

In March 2026, the Loughton site was still operating as a scaffolding yard. Photograph: Martin Godwin/The Guardian

Targeting the rapid growth of AI to boost the economy, the UK government’s proposals to harness the technology have focused on two Nvidia-backed companies: the London-based Nscale and the US company CoreWeave.

Official figures show investments in AI are among the factors helping Britain’s economy to beat expectations of a weaker growth performance this year as the war in the Middle East rattles global business activity.

Nscale is a “neocloud”, one of a number of companies with deep ties to Nvidia that are building the key infrastructure for the AI boom. It is this relationship with Nvidia that meant it and CoreWeave were chosen as key players in the UK’s sovereign AI push, which happened under Starmer.

There is, however, a growing chorus of voices which suggest that neoclouds may be a vulnerability in the broader AI economy, especially as delays pile up across partners.

Driven by hopes of an economic transformation, many are taking on increasingly risky debt, including companies vital to the AI boom. If Nscale pushes back its initial public offering in New York, these vulnerabilities may come into sharper focus.

The former UK deputy prime minister Nick Clegg and the former Meta chief operating officer Sheryl Sandberg are board members at the company. Clegg holds a 0.25% stake that could be worth $88m if the company floats at a $35bn valuation.

It emerged earlier this month that UK Power Networks (UKPN), which owns and maintains the electricity grid across London and the south-east of England, had informed Nscale that it would not be able to supply enough power to the company’s Loughton datacentre until the early to mid-2030s.

Nscale said it was “committed to the project” but the failure to find a quick fix to the power supply issue underlines how much energy has become a hindrance to datacentre development.

The scaffolding yard site has been cleared by Nscale, and the company is investigating whether it can generate power onsite and whether it can speed up the connection process.

An Nscale spokesperson said: “We remain committed to both the Loughton project and the UK, and we are exploring alternative power sources for the site, in addition to other expansion sites in the UK.

“Our relationship with Microsoft remains strong and long-term, and this unfortunate London-wide grid issue has no impact on our other contracts.”Explore more on these topics

Datacentres - UK

Microsoft

AI (artificial intelligence)

Google told to halt work on datacentres in Finland over environmental concerns

OpenAI’s George Osborne says datacentre nimbys holding back Britain

Planning permission for new Scottish AI datacentres suspended for up to a year

Labour rejects Zack Polanski’s call to ‘slam brakes’ on building AI datacentres

Police Scotland warns ‘robust security’ needed to stop attacks on AI datacentres

Datacentre projects face fees for grid access to ease connection queue, Ofgem says

Scotland could freeze datacentre projects in challenge to UK’s AI strategy

Datacentres using 6% of electricity supply in UK and US, research says

Most viewed

来源

The Guardian Technology